Power grid and wind energy don't mesh well

NY Times:

When the builders of the Maple Ridge Wind farm spent $320 million to put nearly 200 wind turbines in upstate New York, the idea was to get paid for producing electricity. But at times, regional electric lines have been so congested that Maple Ridge has been forced to shut down even with a brisk wind blowing.

That is a symptom of a broad national problem. Expansive dreams about renewable energy, like Al Gore’s hope of replacing all fossil fuels in a decade, are bumping up against the reality of a power grid that cannot handle the new demands.

The dirty secret of clean energy is that while generating it is getting easier, moving it to market is not.

The grid today, according to experts, is a system conceived 100 years ago to let utilities prop each other up, reducing blackouts and sharing power in small regions. It resembles a network of streets, avenues and country roads.

“We need an interstate transmission superhighway system,” said Suedeen G. Kelly, a member of the Federal Energy Regulatory Commission.

While the United States today gets barely 1 percent of its electricity from wind turbines, many experts are starting to think that figure could hit 20 percent.

Achieving that would require moving large amounts of power over long distances, from the windy, lightly populated plains in the middle of the country to the coasts where many people live. Builders are also contemplating immense solar-power stations in the nation’s deserts that would pose the same transmission problems.

The grid’s limitations are putting a damper on such projects already. Gabriel Alonso, chief development officer of Horizon Wind Energy, the company that operates Maple Ridge, said that in parts of Wyoming, a turbine could make 50 percent more electricity than the identical model built in New York or Texas.

“The windiest sites have not been built, because there is no way to move that electricity from there to the load centers,” he said.

The basic problem is that many transmission lines, and the connections between them, are simply too small for the amount of power companies would like to squeeze through them. The difficulty is most acute for long-distance transmission, but shows up at times even over distances of a few hundred miles.

...

In Texas, T. Boone Pickens, the oilman building the world’s largest wind farm, plans to tackle the grid problem by using a right of way he is developing for water pipelines for a 250-mile transmission line from the Panhandle to the Dallas market. He has testified in Congress that Texas policy is especially favorable for such a project and that other wind developers cannot be expected to match his efforts.

“If you want to do it on a national scale, where the transmission line distances will be much longer, and utility regulations are different, Congress must act,” he said on Capitol Hill.

...


The Texas Utility commission has already approved lines to transmit the power from West Texas to the municipalities. I suspect it will be a bigger problem in places like New York where regulators tend to have turf battles and throw up road blocks. New Jersey will probably be even worse. It appears that the cost of electricity from wind is going to be much more than the price of the turbines. I think the environmental lobby will also throw up road blocks. It is what they do.

Comments

Popular posts from this blog

Should Republicans go ahead and add Supreme Court Justices to head off Democrats

29 % of companies say they are unlikely to keep insurance after Obamacare

Is the F-35 obsolete?